Agenda
- Review action items from Sprint 2 retro
- Demo of new search feature
- Discuss database migration timeline
- Assign Sprint 3 tasks
- Open floor for questions
Old Business
Sprint 2 Action Items
- Login page redesign - Eve presented the updated mockups. Team approved the new layout. Status: Complete.
- API rate-limiting bug - Bob confirmed the fix was deployed on April 8. No further issues reported. Status: Complete.
- Unit test coverage target (80%) - David noted coverage is currently at 74%. Remaining tests will carry over into Sprint 3. Status: In Progress.
New Business
Search Feature Demo
Carol demoed the new full-text search feature on the staging environment. Key takeaways:
- Search results load in under 200ms on average
- Filters for date range and category are working
- Accessibility audit still pending - assigned to Eve
Database Migration Timeline
Bob proposed migrating from MySQL to PostgreSQL during the April 20-22 maintenance window. The team discussed risks:
- Backup and rollback plan needs to be documented
- Staging migration dry-run scheduled for April 17
- Alice will notify stakeholders by end of week
Sprint 3 Task Assignments
- Finish remaining unit tests - David (High priority)
- Search accessibility audit - Eve (Medium priority)
- Write migration rollback script - Bob (High priority)
- Update user docs for search - Carol (Low priority)
Whiteboard Diagram
Audio Recording
Recording of the full meeting:
Video Recording
Video clip from the meeting:
Meeting Feedback Form
Help us improve future meetings by filling out this quick form.
All fields are optional.
Comments & Questions